Sunday, October 15, 2006

Oct 1, 2006





Once the Foundation was poured we removed the forms. Then I rented a bobcat and backfilled the foundation. I had 20 tons of gravel brought in and placed about 4 inches of it over the top of the backfilled foundation. This took one day. Afterwards I hired Oak Canyon Concrete to come in and do the garage floor. I had no experience doing this so passed on this part of the construction. Here are some pictures of these phases of construction.